Water Improvement Project Update for Ishpeming, Michigan

Ishpeming, MI – Water Improvement Project Update for Ishpeming, Michigan

The updated plan is to tie the water main under Lakeshore Drive into Cliff Street on Wednesday September 6th.  This will require a single lane closure of the northbound lane.  Flag control will be in effect. 

The road will be restored to gravel the same day.  Paving is anticipated to occur in the Sept 13-15 range.  We will provide additional updates as that date is solidified. 

Gravel will be prepped under single lane closure the day prior to paving, the paving will occur under single lane closure as well.  All lane closures will include flag control. 

Thanks!
Jon Kangas, P.E.
DPW Director/City Engineer

 City of Ishpeming
100 E Division Street
P: 906.486.9371
F: 906.486.9551
e: dpwdirector@ishpemingcity.org
w: www.ishpemingcity.org

Submit Press Releases, News, Calendar Items, and Community Events to mediaBrew radio stations WFXD, WKQS, WRUP, GTO, Fox Sport Marquette, and 106.1 The Sound
Click To Submit Press Releases, News, Calendar Items, and Community Events to mediaBrew radio stations WFXD, WKQS, WRUP, GTO, Fox Sport Marquette, and 106.1 The Sound

Marquette, Michigan Calendar; Ishpeming Calendar; Negaunee Calendar; Gwinn Calendar; Negaunee Calendar and Events; Upper Peninsula Calendar of Events; Escanaba Events and Calendar

Related posts

Cable’s Bay and Beaver Island Exhibit at Northern Michigan University (NMU)

Todd P

Ishpeming Renaissance Festival & Art Faire – August 1st

Todd P

Social Justice Advocate Sandra Fluke Speaks at NMU

Todd P

Bill Kirchen in Concert in Gladstone on Saturday, July 8th at Rockin’ The Bay Music Festival

Todd P

Marquette County Conservation District (MCCD) Hosting Leap Day Event on Monday, February 29th

Todd P

Book Review and Signing by Author Jim LaJoie December 11th

Todd P

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More