Water Improvement Project Update for Ishpeming, Michigan

September 5, 2017

Ishpeming, MI – Water Improvement Project Update for Ishpeming, Michigan

The updated plan is to tie the water main under Lakeshore Drive into Cliff Street on Wednesday September 6th.  This will require a single lane closure of the northbound lane.  Flag control will be in effect. 

The road will be restored to gravel the same day.  Paving is anticipated to occur in the Sept 13-15 range.  We will provide additional updates as that date is solidified. 

Gravel will be prepped under single lane closure the day prior to paving, the paving will occur under single lane closure as well.  All lane closures will include flag control. 

Thanks!
Jon Kangas, P.E.
DPW Director/City Engineer

 City of Ishpeming
100 E Division Street
P: 906.486.9371
F: 906.486.9551
e: dpwdirector@ishpemingcity.org
w: www.ishpemingcity.org

Submit Press Releases, News, Calendar Items, and Community Events to Great Lakes Radio Stations WFXD, WKQS, WRUP, WQXO, and WPIQ
Click To Submit Press Releases, News, Calendar Items, and Community Events to Great Lakes Radio Stations WFXD, WKQS, WRUP, WQXO, and WPIQ
Share

Comments